Dabawenyos should protect water sources before it dries up
Water may cover over 70% of the earth’s surface but Dabawenyos should disabuse their minds and stop believing that water is an infinite resource because it is not.
“Dabawenyos are very lucky because we have one of the cleanest potable water in the world---the second actually,” councilor Rachel Zozobrado said. However, she added, we should learn how to use our water wisely and protect our water sources from contaminants.
The world’s water supply is being depleted at an alarming rate and we should not think that we here in Davao are exempted from this worldwide phenomenon, she said. Just recently, Zozobrado said, the United States has admitted that at least 36 States are set to face water shortage in the next five years due to the drying up of their water sources as a result of drought, rising temperatures, urban sprawl, population growth excessive use and waste of water.
The Davao City Water District has already admitted that it is not comfortable with the 70-year lasting capacity projection on underground water sources. DCWD is thus undertaking studies to search for alternative sources of potable water supply. As if this was not enough, a study conducted by the Ateneo de Davao University and the DCWD confirmed the presence of pesticide in the city’s premier watersheds.
“This should be a wake up call to all of us to protect out water sources considering the growing population of Davao and the increasing industrialization of the city,” she said. We should put a premium and prioritize the safety of our water sources if we do not want to end up like the US, Australia, Africa and other countries faced with water shortage, she said. It is not only the US that is experiencing water shortage problems because even Australia is in the middle of a 30-year dry spell.
Zozobrado said the fact that Asia has 60% of the world’s population but we only have about 30% of the world’s fresh water supply. That is a very macro way of viewing the impending water problem but we can confront it by looking at our own water sources, she said.
She said DCWD has opposed the Hedcor-proposed hydroelectric power plants in Tamugan and Panigan rivers despite Hedcor’s assurance that it would not affect the city’s water supply because it already foresees a brewing water problem even without the plant.
“An increase in demand, the presence of pesticides in our water and now the planned construction of a power plant right on top of our water source may just put too much pressure on our aquifers and we would have to rue our decisions later on.” Zozobrado said.
Showing posts with label water project. Show all posts
Showing posts with label water project. Show all posts
Wednesday, February 6, 2008
Commitee Hearing:
Residents of Sitio Cebuda in Bago Oshiro yesterday flocked to the City Council to rally for the implementation of the water project which has been delayed due to several problems involving the Bureau of Plant Industry XI and the Davao City Water District.

Councilor Rachel Zozobrado delivered a privilege speech during last week's City Council session where she lamented the snail-pacing of the project despite the fact that every effort has been done by the barangay to push for its full implementation. She said efforts were made to appease the demands of BPI and this problem was already settled last year so DCWD allowed the hydrotesting. However, up to now, there is still no main water line operating in Sitio Cebuda in Bago Oshiro to the detriment of the residents who have been living in the area without water for several years already.
Councilor Bonifacio Militar scheduled this morning's hearing and invited DCWD and BPI to shed light on the matter. DCWD claimed that they still have to disinfect the line and this requires a payment of P11,839.70. Zozobrado said DCWD should have told the project proponent or the government agencies involved with the project as early as last year after the hydrotesting about the requirement.
DCWD Planning and Design Division chief Engineer Roendo Almonte apologized saying it may have been their fault as they failed to include the said amount in the project design which was the basis of the project cost. However, he assured Zozobrado and Militar that the project will be fasttracked as soon as the disinfection fee is paid.
"Wala man mi kabalo na naa diay pabayaran pa para sa disinfection fee ngano karon man lang nag-ingon ang Water District bisag kami na lanf unta nag tunga-tunga sa barangay para muagas lang ang tubig," barangay captain Jonah Macarayo said.
The Status Of The Water Project In Sitio Cebuda, Bago Oshiro
(l-r)councilors bonicaio militar, rachel zozobrado and bago oshiro bgy. captain jonah macarayo
The water project, which was funded by the late councilor Jesus Zozobrado Jr., suffered hitches after BPI wrote DCWD saying the water project in the area is traversing the property being managed by BPI. It also said the installation of the water pipe will only encourage more squatters in the area.
Councilor Rachel Zozobrado delivered a privilege speech during last week's City Council session where she lamented the snail-pacing of the project despite the fact that every effort has been done by the barangay to push for its full implementation. She said efforts were made to appease the demands of BPI and this problem was already settled last year so DCWD allowed the hydrotesting. However, up to now, there is still no main water line operating in Sitio Cebuda in Bago Oshiro to the detriment of the residents who have been living in the area without water for several years already.
Councilor Bonifacio Militar scheduled this morning's hearing and invited DCWD and BPI to shed light on the matter. DCWD claimed that they still have to disinfect the line and this requires a payment of P11,839.70. Zozobrado said DCWD should have told the project proponent or the government agencies involved with the project as early as last year after the hydrotesting about the requirement.
DCWD Planning and Design Division chief Engineer Roendo Almonte apologized saying it may have been their fault as they failed to include the said amount in the project design which was the basis of the project cost. However, he assured Zozobrado and Militar that the project will be fasttracked as soon as the disinfection fee is paid.
"Wala man mi kabalo na naa diay pabayaran pa para sa disinfection fee ngano karon man lang nag-ingon ang Water District bisag kami na lanf unta nag tunga-tunga sa barangay para muagas lang ang tubig," barangay captain Jonah Macarayo said.